Tag Archives: different data dates

09Mar/16
rusty chain image

Scheduling interlinked projects with different data dates

One of the problems that occurs frequently in integrated schedules during a reporting cycle is that everyone is using different data dates.

Take for example a contractor, they report to you on your week 1 with their latest schedule. This has a data date of the start of week 1. That’s great, except you closed out at the end of week 4 (just like them) so the work is always 4 weeks behind.

So what’s the problem?

Continue reading