Scheduling interlinked projects with different data dates

One of the problems that occurs frequently in integrated schedules during a reporting cycle is that everyone is using different data dates.

Take for example a contractor, they report to you on your week 1 with their latest schedule. This has a data date of the start of week 1. That’s great, except you closed out at the end of week 4 (just like them) so the work is always 4 weeks behind.

So what’s the problem?

Continue reading

25Feb/16

Importing MS Project files into Primavera

Time and time again I see people trying to import MS project files into Primavera and getting into a palaver over import errors.The first thing I see is “you should use MPP to MPX converter” – this is an executable that has been around at least 10 years to my knowledge and generally seems to fail to convert files that fail to import from XML – my preferred way of importing projects.

So why do these files fail?

Continue reading

25Feb/16

Welcome to the first post

I don’t think we ever stop learning about the tools we use at work, so this blog is about tools and techniques I discover or get asked about.  I hope to update this at least monthly.

There’s no such thing as a stupid question, so if you want to know or have something explained, I’ll do the best that I can.

If you’d like to contribute by publishing a guest post, please get in touch using the contact form and as long as it’s a relevant planning post I aim to publish it.  I don’t accept money, neither do I pay for such posts.  There is no advertising on the site.